This document is Addendum No. 01 to the San Juan Police Building Expansion contract (Project 24002). Issued on March 7 2025, it updates the bidding package: it notes the pre‑proposal meeting held on March 4, confirms the bid opening will stay on March 13, states the city will not waive permit fees, explains that the building will stay in use during a two‑phase renovation, specifies that dispatch consoles and the video projector are Owner‑Furnished‑Owner‑Installed, clarifies interior door specifications, requires all mechanical units to be replaced with BACnet‑integrated equipment, and lists which product substitutions are approved and which are not.
| Addendum issue date | 03/07/2025 |
| Pre‑proposal conference | 03/04/2025, 10:00 am |
| Bid opening date | 03/13/2025 |
| Number of construction phases | 2 |
| Owner‑furnished dispatch consoles | Yes |
| Owner‑furnished video projector | Yes |
| Approved material substitutions | Alfrex FR panel, NWR sports floor, Elevate UltraPly 60 mil TPO membrane |
| Rejected material substitutions | Lockers MFG, DynaFit Performance, Laminators Adaptaclad RS |