This is an official invitation for contractors to submit sealed bids for the City of San Juan’s Lift Station No. 6 Relocation Project, which will replace an existing wastewater lift station with a new one and install 1,901 ft of sewer pipe. The project is funded by an EPA STAG CWSRF grant. The notice lists the bid deadline, required bid bond, cost to obtain plans, pre‑bid meeting, and federal requirements for wages, equal‑opportunity, and minority‑owned business participation.
| Bid submission deadline | April 9, 2025, 3:00 PM |
| Pre‑bid conference date | March 19, 2025, 10:00 AM |
| Cost to obtain bid documents | $150.00 (non‑refundable) |
| Required bid bond | 5 % of the bid price |
| Length of new sewer pipe | 1,901 linear feet |
| EPA fair‑share goal – MBE | 24.16 % |
| EPA fair‑share goal – WBE | 17.38 % |