This is Addendum No. 02 (dated March 11 2025) to the original February 14 2025 plans for the San Juan Police Building Expansion. It tells bidders about new or changed items – such as 4 markerboards/tackboards, one projection screen with mount, one set of vehicle‑washing equipment, blind requirements, and electronic signage – and includes revised site‑plan sheets, accessibility slope limits, joint spacing, parking‑stall dimensions, and confirms that city will waive building‑permit fees and that the current building will be vacant during construction.
| Addendum date | 03/11/2025 |
| Original plans date | 02/14/2025 |
| Markerboards and Tackboards quantity | 4 each (4’x6’) |
| Projection screen & mount quantity | 1 each (room P106) |
| Vehicle washing equipment quantity | 1 each (room S105) |
| Maximum accessible route slope | 5% (5/8” per ft) |
| Maximum cross‑slope | 2% (1/4” per ft) |
| Expansion joint spacing | Every 20 ft (max) |