Addendum: Change of Pre‑Bid Date for Lift Station Relocation

original file: ADDENDUM NO. 1
Mar 18, 2025 · San Juan

Open the original document

AI-generated summary — always verify against the original document above.

What is this?

This addendum to the Lift Station No. 6 Relocation project changes the pre‑bid meeting date from March 19 to March 24, 2025, and reminds bidders they must acknowledge receipt of this amendment when they submit their bids.

Key figures

Addendum date March 12, 2025
RFB number 25-005-04-09
Original pre‑bid date March 19, 2025
Revised pre‑bid date March 24, 2025
Requirement to acknowledge receipt Bidder must submit signed acknowledgment with the bid