Addendum No. 3 modifies the original Request for Bid for the City of San Juan Lift Station #6 Relocation Project. It changes the pre‑bid date, sets a new bid‑opening date of April 16, 2025, revises the specifications for the self‑priming pump and its VFD, answers bidders’ questions about the engineering estimate ($3,449,100), the correct voltage (480 V 3‑phase), and the location of the geotechnical report, and reminds bidders to acknowledge receipt and include a 5 % bid bond with their proposal.
| Engineering estimate | $3,449,100.00 |
| New bid opening date | April 16, 2025 at 3:00 p.m. |
| Pre‑bid date change | From April 9, 2025 to April 16, 2025 |
| Required bid security | 5 % of bid price (certified or cashier’s check) |
| Project completion timeline | 548 calendar days after notice to proceed |
| Betterment allowance | $250,000 |
| Number of self‑priming pumps specified | 4 |
| Confirmed electrical voltage | 480 V, 3‑phase |