Addendum 5 – Schedule and Specification Changes for Lift Station #6 Relocation

original file: ADDENDUM NO. 5
Apr 15, 2025 · San Juan

Open the original document

AI-generated summary — always verify against the original document above.

What is this?

Addendum No. 5, dated April 15 2025, modifies the bid documents for the City of San Juan Lift Station #6 relocation project. It shortens the contract schedule from 548 to 365 calendar days, replaces several specification and bid‑form sections, removes the dewatering specification, and provides detailed clarifications for dozens of drawing items (ground‑water control, pump installation, crane capacity, grounding, etc.). Contractors must acknowledge receipt, pay a $150 non‑refundable fee for the documents, and submit bids that incorporate these changes.

Key figures

Addendum number 5
Addendum date April 15, 2025
Original contract duration 548 calendar days
Revised contract duration 365 calendar days
Required crane capacity 2 tons
Non‑refundable document fee $150
Section removed from specifications Section 312319 – Dewatering
Contact for bid questions lmaldonado@sjtx.com (email) – must be sent at least 5 days before bid opening