Addendum No. 5, dated April 15 2025, modifies the bid documents for the City of San Juan Lift Station #6 relocation project. It shortens the contract schedule from 548 to 365 calendar days, replaces several specification and bid‑form sections, removes the dewatering specification, and provides detailed clarifications for dozens of drawing items (ground‑water control, pump installation, crane capacity, grounding, etc.). Contractors must acknowledge receipt, pay a $150 non‑refundable fee for the documents, and submit bids that incorporate these changes.
| Addendum number | 5 |
| Addendum date | April 15, 2025 |
| Original contract duration | 548 calendar days |
| Revised contract duration | 365 calendar days |
| Required crane capacity | 2 tons |
| Non‑refundable document fee | $150 |
| Section removed from specifications | Section 312319 – Dewatering |
| Contact for bid questions | lmaldonado@sjtx.com (email) – must be sent at least 5 days before bid opening |