Addendum No. 5 to the City of San Juan’s Phase Two wastewater‑treatment‑plant improvement RFP (RFP 26‑006‑05‑14). Issued Aug 12 2026, it updates technical specifications, lists the only approved pump and equipment manufacturers, clarifies that the Texas Water Development Board’s BABA rules do not apply, and sets American Iron & Steel (AIS) de‑minimis limits of 5% of total project cost for incidental items and 1% for any single item. Bidders must acknowledge the addendum in their proposals by Aug 18 2026.
| Addendum issue date | August 12, 2026 |
| Bid submission deadline | August 18, 2026 |
| Project number (city) | 008-2025 |
| TWDB project number | 73796 |
| RFP number | 26-006-05-14 |
| De‑minimis cumulative limit (AIS) | 5 % of total project cost |
| De‑minimis individual item limit (AIS) | 1 % of total project cost |