The City of Pharr will hold a public meeting on January 22, 2026 to discuss a $4.1 million wastewater lift‑station project that will replace Lift Station 23 with a new 1.12 MGD lift station, a 24‑inch sewer line and an upgraded 8‑inch force main, with no new user fees or rate increases.
| Public meeting date and time | Thursday, January 22, 2026 at 6:00 P.M. |
| Meeting location | Pharr One Community Center, 1121 E. Nolana Loop, Pharr, TX 78577 |
| Total estimated project cost | $4.1 million |
| New lift station capacity | 1.12 MGD |
| New sewer line size | 24-inch |
| Force main upgrade | replace 6-inch with 8-inch |
| User rate impact | No rate increase required |
| Public review period for environmental documents | 30 days after notice, 8 AM–5 PM at City Hall, 118 S. Cage Blvd., Pharr, TX |