This draft public notice explains the City of South Padre Island’s five‑year Capital Improvement Plan (CIP) for 2024‑2028. It describes the legal requirement to prepare a multi‑year list of major public‑facility projects, how the plan is developed, the criteria used to rank projects, the role of the CIP Advisory Committee, and the schedule for public input and council adoption. The document also sets a $50,000 minimum cost for a project, a 20‑year expected life for assets, and outlines the points system (total 100 points) that prioritizes health‑and‑safety, recreation, funding sources, economic development, service impact, strategic alignment and sustainability.
| Plan period | 2024‑2028 |
| Minimum project cost | $50,000 |
| Expected lifespan of projects | 20 years |
| Total scoring points possible | 100 points |
| Number of advisory committee members | 6 members |
| Public project request deadline | May 2, 2024 |
| Draft CIP presented to Council | June 19, 2024 |
| Public hearing date | August 7, 2024 |