Addendum 3: Convention Center Expansion RFP Clarifications

original file: CMAR Addendum 3
South Padre Island

Open the original document

AI-generated summary — always verify against the original document above.

What is this?

This public addendum (issued April 26 2024) clarifies details for the South Padre Island Convention Center Expansion RFP, including conference sign‑in, corrected construction start date, design deliverable deadlines, proposal submission deadline, and confirms that the Corps of Engineers and an environmental study are not involved, with the GMP tied to 75% completion of construction documents.

Key figures

Addendum issue date April 26, 2024
Pre‑submission conference date and time April 19, 2024 at 10:00 a.m.
Anticipated construction start month April 2025
Schematic Design (SD) completion date May 20, 2024
Design Development (DD) completion date August 30, 2024
Construction Documents (CD) completion date February 7, 2025
Final proposal submission deadline April 30, 2024 at 2:00 p.m.
Corps of Engineers involvement Not anticipated
Generated by gpt-oss:120b