This Addendum No. 1, dated July 25 2024, modifies the RFP #CMR‑2024‑03 for the South Padre Island Convention Center Expansion. It supplies clarifications for bidders, adds the second‑floor plan, revises submission requirements, confirms the project’s schedule (design milestones, construction start in April 2025), provides the owner’s $100 million guaranteed‑maximum‑price budget, lists new facility sizes, and includes contract wording changes and a note about the prohibition‑on‑boycott policy.
| Addendum issuance date | July 25, 2024 |
| RFP number | CMR-2024-03 |
| Anticipated construction start | April 2025 |
| Design deliverable schedule | SD: May 20, 2024; DD: August 30, 2024; CD: February 7, 2025 |
| Owner's GMP budget | $100,000,000.00 |
| New facility sizes | 300‑seat black‑box theater, 10,000 SF ballroom, 27,000 SF exhibition hall, 5,800 SF additional meeting room space |
| Pre‑submission site visit | April 19, 2024 at 10:30 a.m. |