Addendum to South Padre Convention Center Expansion RFP (July 2024)

original file: ADDENDUM No. 1 CMR-2024-03
South Padre Island

Open the original document

AI-generated summary — always verify against the original document above.

What is this?

This Addendum No. 1, dated July 25 2024, modifies the RFP #CMR‑2024‑03 for the South Padre Island Convention Center Expansion. It supplies clarifications for bidders, adds the second‑floor plan, revises submission requirements, confirms the project’s schedule (design milestones, construction start in April 2025), provides the owner’s $100 million guaranteed‑maximum‑price budget, lists new facility sizes, and includes contract wording changes and a note about the prohibition‑on‑boycott policy.

Key figures

Addendum issuance date July 25, 2024
RFP number CMR-2024-03
Anticipated construction start April 2025
Design deliverable schedule SD: May 20, 2024; DD: August 30, 2024; CD: February 7, 2025
Owner's GMP budget $100,000,000.00
New facility sizes 300‑seat black‑box theater, 10,000 SF ballroom, 27,000 SF exhibition hall, 5,800 SF additional meeting room space
Pre‑submission site visit April 19, 2024 at 10:30 a.m.
Generated by gpt-oss:120b