This is a public pre‑bid notice for the Laguna Boulevard Street and Drainage Improvements project in South Padre Island. It announces a September 30, 2024 meeting, sets the sealed‑bid deadline for October 15, 2024, and states that work is expected to begin in December 2024 and last about 60 calendar days. The notice outlines the scope (finishing punch‑list items such as slope correction, curb and gutter work, and handicap‑ramp repairs), required bid bond (5 % of the bid), normal work hours (7 a.m.–6 p.m., Monday‑Friday), and basic contractor responsibilities. It also lists detailed quantities for demolition, paving, curb, drainage and miscellaneous items that bidders will price.
| Public meeting date and time | September 30, 2024 at 10:00 a.m. |
| Bid submission deadline | October 15, 2024 at 2:00 p.m. |
| Projected project start | December 2024 |
| Contract duration | 60 calendar days (may be more) |
| Required bid bond | 5 % of bid price |
| Standard work hours | Monday–Friday, 7:00 a.m. to 6:00 p.m. |
| Milling asphalt pavement quantity | 1,211 square yards |
| Number of stainless‑steel posts | 23 posts |