The Popular Annual Financial Report (PAFR) for the City of South Padre Island summarizes the city’s financial activities and highlights from the fiscal year that started on October 1 2018 and ended on September 30 2019. It pulls key data from the audited 2019 Comprehensive Annual Financial Report and presents the city’s major projects, revenue sources, expenditures, and recognitions. Major items covered include updates to the city’s Comprehensive Plan, progress on the Tompkins Park redesign, sidewalk and street‑reconstruction work on Padre Boulevard, the completion of a multimodal transit facility, and awards for financial management. The report also lists the elected officials, leadership team, and provides a snapshot of community demographics and economic factors.
| Fiscal year covered | October 1 2018 – September 30 2019 |
| Padre Boulevard sidewalk length | approximately 4.6 miles |
| Phase 1 street reconstruction cost | approximately $1.9 million |
| Phase 2 street reconstruction cost | approximately $40 7,000 |
| Tompkins Park design completion | 90 % complete |
| Transit facility parking capacity | 125 vehicles |
| Transit building size | 11,772 square feet |
| TIGER grant for transit building | $4.6 million |